A _____ represents the sequence of the activities needed to complete the project.

A) work break down structure
B) scope of work
C) project logic diagram
D) run chart
E) step change

Work Break Down Structure

A hierarchical decomposition of a project into smaller components, helping in organizing and defining the total scope of the project.

Scope Of Work

A detailed document that describes the work activities, deliverables, and timelines for a project or a portion of a project.

Project Logic Diagram

A graphical representation that illustrates the sequence and inter-relationship of tasks within a project.

  • Comprehend the approach and necessity of outlining a project's parameters, time plan, and monetary estimates.
verifed

Verified Answer

AK
Alexander KarvounisOct 21, 2024
Final Answer: