Ignoring the risk level of a project can cause a firm to reject a profitable project.
Profitable Project
A project that generates more revenue than its operating and other costs.
Risk Level
The degree of variability in investment returns, associated with the level of uncertainty in achieving gains or losses.
- Acknowledge the necessity of incorporating project risk considerations into investment analysis.
Verified Answer
BM
Learning Objectives
- Acknowledge the necessity of incorporating project risk considerations into investment analysis.