The initiation phase typically ends:
A) when there is sufficient information to begin developing a detailed schedule and budget.
B) once the project manager has been chosen.
C) after project execution resources such as office space and computers) have been acquired.
D) when the project scope has been clearly defined and all stakeholders are in agreement.
E) once the punch list has been completed.
Initiation Phase
The initial step in a project management process that involves defining a new project or a new phase of an existing project, securing necessary approvals to proceed.
Detailed Schedule
An in-depth timetable that outlines the timing and sequence of project activities, milestones, and deadlines.
- Understand the various stages of the project life cycle and identify the critical tasks executed within each stage.
- Understand the initiation phase's endpoint and the criteria signaling readiness for the subsequent phase.
Verified Answer
JD
Learning Objectives
- Understand the various stages of the project life cycle and identify the critical tasks executed within each stage.
- Understand the initiation phase's endpoint and the criteria signaling readiness for the subsequent phase.
Related questions
Identifying and Acquiring the Project Management Infrastructure Is an Activity ...
The Emphasis of the _____ Phase Is to Develop an ...
Which of the Following Activities Is Typically Performed During the ...
Project Phases Do Not Have Clear-Cut End Dates and Some ...
The Activities That Occur Within the Initiation Phase Are the ...