Which of the following statements regarding CPM networks is true?

A) There can be multiple critical paths on the same project, all with different durations.
B) The early finish of an activity is the latest early start of all preceding activities.
C) The late start of an activity is its late finish plus its duration.
D) If a specific project has multiple critical paths, all of them will have the same duration.
E) If a specific project has multiple critical paths, all of them will have negative slack.

CPM Networks

Stands for Critical Path Method Networks, which are used in project management to identify the longest sequence of dependent tasks and the minimum completion time for the whole project.

Critical Paths

The sequence of stages determining the minimum time needed to complete a project, where any delay in the critical path tasks will directly affect the project completion date.

  • Gain insight into the relevance and implementation of critical path analysis within project management.
verifed

Verified Answer

AS
Abraham SetiaNov 07, 2024
Final Answer:
Get Full Answer